The mechanic’s lien process is comprised of three parts: preliminary notice, mechanic’s lien (or bond claim), and foreclosure or suit to enforce the claim.
The first step to secure mechanic’s lien rights on a private project (or
bond claim rights on a public project) is to serve a preliminary notice. A preliminary notice is not a mechanic’s lien, it’s a prerequisite to filing a mechanic’s lien and identifies you as a party furnishing materials or services to a construction project. Statutory preliminary notices are governed by state law and typically must be served upon the general contractor and/or project owner within the specified timeframe. However, it’s recommended you serve the notice upon all parties within the ladder of supply to increase transparency and prioritize your payment. If you don’t serve the preliminary notice, and the notice is required, you could invalidate your right to file a mechanic’s lien on the project. Currently,
43 states in the U.S. and one province in Canada have provisions for a preliminary notice to be served prior to filing the lien. Furnishing to a project in a state where no
preliminary notice is required? Consider serve a non-statutory notice.
- Statutory Preliminary Notice: a statutory preliminary notice is a notice created by a state’s law. This notice is often served upon the owner and/or prime contractor as a precondition to filing a lien or serving a bond claim.
- Non-Statutory Preliminary Notice: a non-statutory notice is a notice (not created by state law) served upon parties on the ladder of supply, advising all parties that you are furnishing to a project.
A preliminary notice goes by different names depending on the state in which it’s served. Some alternative names include notice to contractor, notice to owner, notice of furnishing and prelien notice.
The final step is enforcing your claim. A suit, or lawsuit, is an action in a court of law to enforce a claim. Is this the same as foreclosure? Foreclosure is a legal action to enforce a lien against real property with the purpose of having the property sold to satisfy the lien. Suit may lead to foreclosure. It has been our experience that suit does not usually result in foreclosure/sale of the property; more often, during the suit phase, settlement agreements are reached without the need for sale of the property.
How Do Mechanic’s Liens Work?
When a contractor, subcontractor, or material supplier completes work on a property but is not paid, they can file a mechanic’s lien as a legal claim for the unpaid amount. This lien becomes an encumbrance that clouds the title, making it difficult to sell or refinance the property. A title search will reveal any liens, alerting potential buyers to the issue. Because buyers typically do not want to take on responsibility for unpaid debts, they often require the lien to be satisfied (meaning the contractor, subcontractor, or supplier must be paid) before completing the purchase. If the property owner cannot pay the debt, the contractor has the right to foreclose on the property, forcing a sale to recover the money owed.
What Are the Deadlines?
How long do you have to file a mechanic’s lien?
Mechanic’s lien deadlines vary by state, though they are often calculated from the date of last furnishing or project completion. Once you have confirmed the deadline, don’t wait until the last minute to file the lien. Various factors (inclement weather, county closures, state holidays and the wait-times for document recording, etc.) can cause major delays in recording. When unforeseen circumstances arise, other methods of service may be required, which can be costly.
Notice of Lien Requirements
The mechanic’s lien should be recorded with the appropriate recording office and, as a best practice, a copy should be served upon all parties in the ladder of supply. Frequently, the owner and general contractor are required to receive a copy of the lien, though this will vary by state. For example, in California, the mechanic’s lien
“verified and containing the information required in subdivision (a), shall be accepted by the recorder for recording and shall be deemed duly recorded without acknowledgment.” Further, “…(c) A copy of the claim of mechanics lien, which includes the Notice of Mechanics Lien required by paragraph (8) of subdivision (a), shall be served on the owner or reputed owner… (2) If the owner or reputed owner cannot be served by this method, then the copy of the claim of mechanics lien may be given by registered mail, certified mail, or first-class mail, evidenced by a certificate of mailing, postage prepaid, addressed to the construction lender or to the original contractor.” –
CA Civ. Code 8416
Who Should Receive the Mechanic’s Lien?
Generally, the lien should be served upon the owner and general contractor; however, it is recommended to serve a copy on all parties involved. The more people that know you haven’t been paid the more pressure they will put on the appropriate party to encourage payment.
How Is a Mechanic’s Lien Enforced?
A mechanic’s lien is enforced through litigation. A
suit, or lawsuit, is an action in a court of law to enforce a claim. Is this the same as foreclosure? Foreclosure is a legal action to enforce a lien against real property with the purpose of having the property sold to satisfy the lien. Suit may lead to foreclosure. During litigation, it may come to light that debts can only be paid if the property is sold & the proceeds are then used to square up the debts. Please understand, it has been our experience that suit does not usually result in foreclosure/sale of the property; more often, during the suit phase, settlement agreements are reached without the need for sale of the property.
Lien Enforcement Deadlines
Suit to enforce the mechanic’s lien must be filed within the timeframe outlined by each state’s statute. In Georgia (
O.C.G.A. § 44-14-367), suit must be filed within 365 days from filing the lien, or within 60 days from a Notice of Contest of Lien served by the owner. Whereas, in Ohio (
ORC Sec. 1311.01-1311.21) you must file suit to enforce the lien within 6 years from filing the lien, and within 60 days of being served with a notice to commence suit.
Lien Enforcement Challenges
Lien enforcement challenges could widely vary, but may include complex property ownership (including
lien on leasehold situations), issues of priority, back charges/change orders or disputes, and failure to strictly comply with statutory requirements.
Priority Issues
If there are multiple mechanic’s liens filed on a given property, issues of priority may arise. The determination of priority is up to arbitration or the court, though some state laws do outline who priority. If we refer to Florida’s statute,
F.S. Title 40, Section 713.07, it reads in part:
“(1) Liens… shall attach at the time of recordation of the claim of lien and shall take priority as of that time. (2) Liens… shall attach and take priority as of the time of recordation of the notice of commencement, but in the event a notice of commencement is not filed, then such liens shall attach and take priority as of the time the claim of lien is recorded.”
Are there Limitations?
Limitations may include whether the lien is being filed in a
full balance or unpaid balance lien state. In a Full Balance Lien State, the lien is generally enforceable for the full amount owed, regardless of payments made by the owner. An Unpaid Balance Lien State protects the owner from having to pay twice for materials and labor provided to their construction project. When your lien is limited to the unpaid portion of the general contract, it is critical to file the lien as soon as possible, so that it is filed prior to the owner paying the prime contractor. Additionally, not all parties payment rights are protected under a mechanic’s lien. Although statutes vary by state, and ever case is different, if you are a material supplier furnishing to a material supplier, your lien rights may be questionable. Also, based on state statute, rights may be limited when contracting with a
lower-tier subcontractor.
Limited Recovery
Recovery may be limited by many factors. Depending on the state, you may be unable to recover legal fees (recovery would be limited to the value of materials or services provided to the construction project). In some cases, the owner and/or GC may have insufficient funds to cover all debts, and you may only recover a pro-rata share.
What Happens to the Mechanic’s Lien when I Receive Payment?
When you have filed a mechanic’s lien and then receive payment for the outstanding debt, you must file a release of lien. A
release of lien is a document recorded upon satisfaction of a claim of lien. When a lien is filed, it becomes public record and encumbers the property. Unless a release of lien is filed, the public record will continue to reflect the lien, and it will appear as an encumbrance. As best practice, prior to releasing the lien you should confirm you have received payment in full and the payment has cleared. If you release the lien and an issue arises with payment, you may not be able to refile the lien.
What Is a Lien Waiver?
A
lien waiver is a signed document in which the would-be lien claimant agrees to waive rights to its claim based on payment received. Lien waivers are either conditional or unconditional and partial or final.
- A conditional lien waiver is conditioned up receipt and clearance of the payment. If the terms of a conditional lien waiver aren’t met, the waiver becomes null and void. For example, if you don’t receive payment or the payment doesn’t clear the bank, you have a right to file a mechanic’s lien to recover the payment.
- An unconditional lien waiver is not conditioned upon receipt and clearance of payment. Without conditions, you lose leverage. If you don’t receive payment or the payment doesn’t clear the bank, you’re unable to file a mechanic’s lien because you waived your right to file the mechanic’s lien.
Conditional lien waivers are preferred over unconditional lien waivers, because the “conditions” provide the creditor with leverage, in the event payment is not received or does not clear.
The Value of Commercial Credit Collection Services and Construction Attorneys
Mechanic’s liens are powerful, and the power lies in the details. The nuances (deadlines!) and complexities of each state’s statute make the mechanic’s lien process cumbersome and time consuming. Save time, money, and frustration by partnering with mechanic’s lien experts. Whether you have a mechanic’s lien process in place or are just starting to explore the benefits of mechanic’s liens, NCS Credit is ready to develop and manage the process for you. The mechanic’s lien process, including preliminary notices, mechanic’s liens, bond claims, and foreclosure, is our specialty. We are uniquely positioned to provide you with a comprehensive mechanic’s lien program. In addition to our in-house mechanic’s lien experts, we maintain a strong national network of construction attorneys. These attorneys specialize in mechanic’s lien enforcement and
construction litigation. NCS Credit is the industry’s only full-service provider of mechanic’s lien, UCC filing, and commercial collection services. Powered by our knowledgeable staff and fueled by technology, we will simplify your process and deliver a best-in-class experience. With unparalleled industry expertise, we understand the complexities of commercial construction credit.