Illinois Mechanic’s Lien and Bond Claim Rights
What You Should Know About Protecting Lien & Bond Claim Rights in Illinois In 2019, Illinois HB2722 passed, which added protection under the payment...
Furnishing to a private construction project in Wisconsin? Today’s post is all Wisconsin. Let’s review what you should know about mechanic’s lien, bond claim, and lien on funds rights for private construction projects!
Wisconsin mechanic’s liens are governed by Wis. Stat. Sec. 779.01 through 779.17. For both commercial and residential projects, the mechanic’s lien is enforceable for the full amount owed, regardless of payments made by the owner – this is known as a full balance lien state.
Generally, there is no statutory requirement for serving a preliminary notice to secure your mechanic’s lien rights on commercial projects. However, residential projects do have a preliminary notice. On residential projects, the notice deadline is different if you are the prime contractor versus any other party in the ladder of supply.
For both commercial & residential projects, the mechanic’s lien is a two-step process: notice of intent + mechanic’s lien. You should serve the notice of intent at least 30 days prior to filing the lien and you should file the lien within 6 months from your last furnishing. In the event you need to pursue suit to enforce your lien, you should file suit within 2 years from filing the lien.
In Wisconsin, if the contract between the owner and prime contractor contains a provision for payment by the prime contractor of all claims, and the prime contractor provides a payment bond, then lien rights are eliminated for all lien claimants except the prime contractor. What do all other parties do? Pursue a bond claim and/or lien on funds.
To secure your right to make a claim against the prime contractor’s payment bond, serve a notice upon the prime contractor within 60 days after first furnishing materials or services. It is then recommended you serve a bond claim upon all parties within 90 days after last furnishing. If filing suit is needed, it should be filed within 1 year after completion of contract work. (You can find additional information in Wisconsin statute: Wis. Stat. Sec. 779.03 through 779.036)
Generally, for a lien on funds, no preliminary notice is required. You should serve the lien upon the owner and any mortgage lender before payment is made to the prime contractor or subcontractor. The lien attaches to the unpaid funds.
If neither the prime contractor nor subcontractor disputes the lien by written notice to the owner and the lien claimant, within 30 days after service of the lien, the amount liened shall be paid to the claimant on demand.
The deadline to proceed with suit to enforce the Lien on Funds is a bit trickier than it is for the mechanic’s lien or bond claim.
Questions about securing your payment rights on private Wisconsin projects?
We’re here to help!
What You Should Know About Protecting Lien & Bond Claim Rights in Illinois In 2019, Illinois HB2722 passed, which added protection under the payment...
Nebraska Construction Lien (aka Mechanic’s Lien) and Bond Claim Rights I once heard the state insect of Nebraska is the honeybee. So, I thought it’d ...
North Dakota Mechanic’s Lien and Bond Claim Rights “North Dakota. Be Legendary.” This might be my all-time favorite state slogan. It’s… well, it’s...