Service Area: Notice and Mechanic’s Lien Services

Prelien Notice Mistake Invalidates Mechanic’s Lien

Prelien Notice Mistake Invalidates Mechanic’s Lien in Minnesota

Today’s case is an unfortunate example of how one contractor lost its mechanic’s lien rights because its preliminary notice failed to meet the requirements outlined by Minnesota’s statute.

Here’s the Story

  • The Case: Niewind v. Carlson, 628 N.W.2d 649 (Minn. App., 2001)
  • The State: Minnesota
  • The Mistake: Preliminary notice did not meet statutory requirements
  • The Consequence: Loss of mechanic’s lien rights

In Niewind v. Carlson, 628 N.W.2d 649 (Minn. App., 2001), Chuck Niewind dba C & N Construction (Niewind), contracted with the Carlsons to build a home for the price of $291,725. Niewind provided extra work and claimed an additional $24,345.45 was due.

The Carlsons admitted Niewind completed extra work and that they owed him an additional $21,942.66 for the surplus work, but the Carlsons refused to pay anything because they claimed there were construction defects in the amount of $100,000.

Preliminary Notice Statute & Securing Lien Rights

Due to lack of payment, Niewind proceeded to secure his mechanic’s lien rights by serving a preliminary notice, filing a mechanic’s lien and ultimately he filed an action to foreclose the mechanic’s lien (aka suit).  The Carlsons asserted the mechanic’s lien could not be enforced because Niewind’s preliminary notice didn’t comply with Minnesota’s lien statutes.

Under the mechanic’s lien statute for Minnesota, a prelien notice (aka preliminary notice) must be in at least 10-point bold type, if printed, or in capital letters, if typewritten.  Minn. Stat. § 514.011, subd. 1, states that anyone who fails to provide notice shall not have a valid lien.

514.011 NOTICE.
Subdivision 1. Contractors.

Every person who enters into a contract with the owner for the improvement of real property and who has contracted or will contract with any subcontractors or material suppliers to provide labor, skill or materials for the improvement shall include in any written contract with the owner the notice required in this subdivision and shall provide the owner with a copy of the written contract. If no written contract for the improvement is entered into, the notice must be prepared separately and delivered personally or by certified mail to the owner or the owner’s authorized agent within ten days after the work of improvement is agreed upon. The notice, whether included in a written contract or separately given, must be in at least 10-point bold type, if printed, or in capital letters, if typewritten and must state as follows:

“(a) Any person or company supplying labor or materials for this improvement to your property may file a lien against your property if that person or company is not paid for the contributions.

(b) Under Minnesota law, you have the right to pay persons who supplied labor or materials for this improvement directly and deduct this amount from our contract price, or withhold the amounts due them from us until 120 days after completion of the improvement unless we give you a lien waiver signed by persons who supplied any labor or material for the improvement and who gave you timely notice.”

A person who fails to provide the notice shall not have the lien and remedy provided by this chapter.

Niewind’s prelien notice was in 11-point font, complying with the first requirement, but it was not in bold or capital letters.

The Consequence? An Invalidated Mechanic’s Lien

The district court declined to invalidate Niewind’s mechanic’s lien based on this technicality; however, the appellate court reversed that decision. The appellate court stressed that the statute requires strict compliance; prelien notices must be in bold type or capital letters, and the statute is clear and unambiguous as to the consequences for failure to provide proper notice.

This left Niewind’s mechanic’s lien unenforceable due to lack of compliance with Minnesota’s mechanic’s lien laws.

It’s a Tough Lesson

Niewind’s invalidated mechanic’s lien can be an auspicious warning. Mechanic’s Lien laws vary state to state, and yes, one state may be more lenient than another, but it’s best to follow the statute to the letter.

Remember, mechanic’s lien laws are often complicated and are not always written in a straightforward manner; however, strict adherence to these laws is required. It’s unfortunate that something as simple as using the wrong font can invalidate the rights of a lien claimant, but the laws are in place to protect all parties.

How To Find a Construction Law Attorney

How to Find an Attorney that Understands the Intricacies of Construction Law

You sent your preliminary notice; your customer’s invoices became past due.

You sent a demand letter; your customer didn’t budge.

You filed a mechanic’s lien, miscommunication is running rampant between the parties within the contractual chain, and yet you still aren’t paid…

It’s Time to File Suit.

Suit” is an action in a court of law to enforce a claim.  (When enforcing a lien, suit is also referred to as “foreclosure”.)  Since suit is an action brought before the courts, it needs to be handled by an attorney – preferably an attorney that specializes in construction law. But how do you find an attorney that understands the intricacies of construction law, is able to take on your case, and do so at a moderated cost?

Many credit professionals turn to NCS and say “Help!”, because our network of attorneys provides extraordinary expertise.  Due to the valuable relationship cultivated with NCS, our attorneys provide their services at lower hourly rates.  But for those who would prefer to take the path less traveled, begin the search for the right attorney.

Hiring an attorney, a new vendor, should be very similar to the way you hire employees and qualify customers for credit. Before you commit, make sure you can create a comprehensive picture of the attorney’s qualifications, experience & costs.  NCS recommends asking the following questions & taking the following steps when looking for an attorney to take on your suit/foreclosure efforts.

First: the daunting task of actually searching for & locating an attorney.

  • Ask for a referral: ask your business circles for attorney recommendations. Often times, social networks, like LinkedIn, may assist in this effort.
  • Search the web: there are many websites available, but do your due diligence to ensure you are selecting reputable sites.

Second: the interview process.

Yes, you need to interview a perspective attorney. They are going to become an extension of your business – you are hiring them to assist you with your accounts receivable. Here are a few interview questions:

  • What are your core competencies? i.e. Are you familiar with mechanic’s lien/construction law and do you practice these areas of law regularly? If you are interviewing an attorney that typically handles divorce cases, but once in a blue moon handles construction litigation, then perhaps it would be better to move on to the next attorney in your list. Think of it this way: If you need to have a tumor removed from your brain, would you want to go to a general surgeon who dabbles in many types of surgeries or a neurosurgeon that specializes in tumor removal?
  • Have you handled cases like this in the past? You aren’t asking for specifics on a particular case (which is protected by attorney-client privilege), you are simply asking if the attorney has represented a lien claimant in a suit case similar to yours.
  • What is your hourly rate and what is included in that hourly rate? It’s important to know what is included in that hourly rate. Some attorney’s charge separately for research, phone calls and document drafting & mailing, while others are willing to bill on a contingency fee basis.
  • How frequently will you update me on the events of the case? Open communication is imperative, so set an expectation up front. If the attorney provides updates monthly, are you OK with that? Would you prefer an attorney update you weekly? If so, ask.

Finally: embark on the relationship, but do so with caution.

Once you have found, qualified & committed to an attorney, trust the attorney to complete the task at hand efficiently and effectively, but do not go into auto-pilot mode, be an active participant in your case. Of course, if the idea of qualifying an attorney to handle your suit has successfully made your head spin and your stomach knot up with anxiety, contact NCS.

North Carolina Notice to Lien Agent

North Carolina: the Lien Agent & the Notice

The mechanic’s lien law in North Carolina experienced a rather large change in April 2013: the introduction of the Lien Agent. I would like to believe that the Lien Agent is a super-secret spy infiltrating the construction credit industry on behalf of mechanic’s lien claimants everywhere! Alas, while the Lien Agent may have some super powers, like preventing hidden liens, it’s not quite the super spy I’d hoped for.

Why is there a Lien Agent in North Carolina?

North Carolina had a “hidden lien” problem with construction projects. The mechanic’s liens weren’t hiding under bushes or behind trees, but rather hiding from future property buyers and lending companies. So, the North Carolina legislature came up with a solution: designate a party, for each private construction project, who must receive notification from any contractor or subcontractor supplying materials or labor to said project.

Who is the Lien Agent?

The Lien Agent is designated by the property owner if the project is $30,000.00 or more at the time the original building permit is issued, or, if no building permit is required, at the time the contract is entered into by the owner. According to LiensNC “Only title insurance companies and title insurance agents licensed to do business in North Carolina can serve as Lien Agents”

When should I notify the Lien Agent?

Serve the Notice to Lien Agent within 15 days from first furnishing labor or materials OR before the property is conveyed to a bona fide purchaser.

Is the Notice to Lien Agent the same as the Notice of Subcontract?

NO! These are two separate documents and you should serve both notices in order to protect your mechanic’s lien rights.

  • Serve a Notice of Subcontract on the prime contractor if the owner or prime contractor has properly filed and posted a Notice of Contract.
  • Serve Notice to Lien Agent within 15 days from first furnishing labor or materials or before the property is conveyed to a bona fide purchaser.

Will I always need to serve the Notice to Lien Agent and the Notice of Subcontract?

No, there may be circumstances when one or both of these notices may not be required. However, it is a best practice to serve these notices on every project to avoid any surprises when it’s time to file a mechanic’s lien or proceed with suit to enforce the mechanic’s lien. It would be awful to find out that your mechanic’s lien is invalid because you didn’t serve a notice, serve the correct notice or serve the correct parties with a copy of the notice.

How do I find out who the Lien Agent is?

You could take advantage of a service provider, like NCS, or you could visit the LiensNC website.

“The LiensNC website is a collaborative effort of NIC Services, LLC (NIC) and LiensNC, LLC (LLC) to provide a web-based online system to facilitate the filing of notices to the mechanics lien agents (MLA). The singular goal of this massive effort is to make the filing and finding of MLA notices as simple and as fast as possible for all users. This has been a joint effort of the title insurance underwriter members of the LLC.”

Do you have additional questions about the Notice to Lien Agent or need assistance with serving the Notices? Contact us today!

Serve Notice After First Furnishing

Serve the Preliminary Notice AFTER You Begin Furnishing

Did you know some states require the preliminary notice to be served after you begin furnishing? Georgia, Iowa, Nevada & Wisconsin case law and/or statute instruct the claimant to serve the required preliminary notice once furnishing has commenced.

Georgia, Iowa, Nevada, and Wisconsin

Georgia

  • Private Projects: Serve Notice to Contractor within 30 days after first furnishing materials or services or within 30 days from the filing of the Notice of Commencement, whichever is later.
  • Public Projects: Serve Notice to Contractor within 30 days after first furnishing materials or services or within 30 days from the filing of the Notice of Commencement, whichever is later.

Iowa

  • Private Projects: Serve notice within 30 days after first furnishing materials or services.
  • Public Projects: Serve notice within 30 days after first furnishing materials or services.

Nevada

  • Private Projects: Serve notice after first furnishing materials or services, but within 31 days from first furnishing materials or services.
  • Public Projects: Serve notice after first furnishing materials or services, but within 30days from first furnishing materials or services.

Wisconsin

  • Residential Projects: Serve notice within 60 days after first furnishing materials or services (10 days if a prime contractor).
  • Public Projects: Serve notice within 60 days after first furnishing materials or services.

Most of us are familiar with states like California: serve the preliminary notice within 20 days of first furnishing. Typically, in states like California, it’s OK to serve the notice before you begin furnishing, as long as you serve the notice within the 20 days. But, as with everything in the construction credit industry, not all state statutes are the same.

Additional Resources from NCS

Interested in knowing which states have preliminary notice requirements for private projects (commercial & residential) or public projects? Check out these NCS Quick References!

For additional clarification on each state’s statute, please take a look at The National Lien Digest© or consult an attorney.

Small Mistake High Price in Mechanic’s Liens

In the Field of Mechanic’s Liens, a Small Spelling Error has Large Price Tag

Mechanic’s Lien laws are notoriously complex and courts across the nation are often strict when determining compliance with statutes.  A New York court issued a decision which highlights the high costs of seemingly minor technical mishaps in the filing of a mechanic’s lien.

The Supreme Court of New York

New York County ruled in A. & L. Construction Corp. v. East Harlem Developers, LLC, that the plaintiff, A. & L. Construction Corp., lost the ability to foreclose its mechanic’s lien due to a minor error in the spelling of its name on the lien.

A. & L. Construction (A. & L.) filed proceedings to foreclose a mechanic’s lien against East Harlem Developers in the amount of $150,229.79.  The defendant, East Harlem Developers, filed a motion for summary judgment alleging the mechanic’s lien was invalid because the plaintiff, A. & L. Construction, is not the corporation named on the mechanic’s lien and the contract.

Evidently, on both the mechanic’s lien and the contract, the entity listed is “A&L Construction Corp.,” not “A. & L. Construction Corp.”  The defendant alleged it never did business with A&L Construction, which had different owners than A. & L., never did business with the defendant, and was dissolved three years before the parties contracted and work begin on the project.

The court explained that A. & L. had actually filed a previous action to enforce its mechanic’s lien which was dismissed for lack of standing.  A. & L. was instructed to re-file an action with its correct legal name and to correct its corporate name on the mechanic’s lien.  While A. & L. filed the current action with the correct name, it did not amend the existing mechanic’s lien.

“The Mechanic’s Lien is Unenforceable!”

A. & L. contended it was a mere scrivener’s error that misspelled the corporate name on the contract and mechanic’s lien. It urges that this minor error should not affect the validity of its mechanic’s lien.

The court, however, disagreed.

It turned to the language of the lien statute which requires the notice of lien state the name of the lienor. It found A. & L. failed to provide any evidence that the spelling was a scrivener’s error besides the plain assertion.  Accordingly, the court held the lien to be unenforceable and granted summary judgment to East Harlem.

The case of A. & L. illustrates the harsh consequences of even a minor error in the realm of mechanic’s liens. The difference between “A&L” and “A. & L.” is miniscule.  It is hardly even noticeable; a difference of two periods and two spaces.  A. & L. had likely taken to referring to itself as the simplified A&L for shorthand purposes, and failed to correct itself on official documents.

To a layperson, the error appears minor and understandable.  However, to the New York court, the error was significant enough to cost A. & L. a $150,229.79 mechanic’s lien.

What Are Joint Check Agreements?

What Are Joint Check Agreements?

No, it has nothing to do with twisting your arm while depositing a check at the bank, although I’m certain some may believe this to be true. A Joint Check Agreement is an agreement between multiple parties, allowing one party to make payment through a check issued to two or more payees. These types of agreements require the consent of multiple parties (i.e. the GC & the Sub or the Owner & the GC) and are often used as an additional tool in managing risk associated with construction credit.

What’s the benefit of a Joint Check Agreement?

The primary benefit of a joint check agreement is the additional security it can provide.

  • General Contractors like joint check agreements because they help to ensure the subcontractor will pay its suppliers with the appropriate funds (i.e. Circumvent robbing Peter to pay Paul).
  • Material Suppliers and other parties contracted with subcontractors like joint check agreements for added security on a potentially risky credit situation. (i.e. perhaps there is a lack of solid credit info on the general contractor)

What information should be included in a Joint Check Agreement?

Let’s break down the contents of a sample Joint Check Agreement provided by The Credit Research Foundation.

First, include the date of the agreement, the invoice(s)/purchase order(s) to be covered under the agreement, your company name & address as well as your customer’s name & address.

Date Purchase Order Number
Your Company Name Your Customer’s Name (Party 2)
Your Company Address Party 2 Address
Your Company City/State/Zip Party 2 City/State/Zip

Gentlemen:

YOUR COMPANY NAME has been requested by PARTY 2 to furnish certain (specify:  parts, components, etc.) on credit under purchase order number: ___________________ dated: ________________. The project is identified by PARTY 3 purchase order # __________________, dated: _________________.

Next, identify the authorized signors (the individual at each company that is permitted to execute this type of agreement) as well as the terms and conditions of the sale.

PARTY 2 and PARTY 3 understand and agree that: (1) the undersigned signors are authorized agents of said companies and are duly empowered to enter into and make a binding agreement on behalf of their respective companies; (2) YOUR COMPANY NAME standard terms and conditions of sale which appear on each of YOUR COMPANY NAME invoice and the application of credit shall govern all sales of goods and/or equipment from YOUR COMPANY NAME to PARTY 2 in accordance with its contract with PARTY 3.

Make sure to include wording that covers the materials/labor provided for the particular project. Including a specific project helps alleviate “robbing Peter to pay Paul” (i.e. monies paid are for that particular project).

Applicable only to the products furnished by YOUR COMPANY NAME and as a condition precedent to furnishing said materials for use and incorporation in the aforementioned project, YOUR COMPANY NAME requests that until it is paid in full, all payments made or to be made by PARTY 3 to PARTY 2 with respect to said project, be made payable by check or checks jointly payable to PARTY 2 and YOUR COMPANY NAME. It is understood that all payments shall be timely and in the form of an immediate and unconditional negotiable instrument. Upon issuance of a check by the PARTY 3, it shall be promptly endorsed by PARTY 2 and delivered to YOUR COMPANY NAME. It is understood that this is a continuing Agreement applicable to the original purchase order and the YOUR COMPANY NAME invoice(s) and to any subsequent billing related to this project only.

Identify what actions should be taken in the event one party fails to uphold their end of the agreement. Lastly, include language prohibiting the altering of said agreement and include spaces for all three parties to sign.

Should PARTY 2   refuse to endorse any joint check tendered by PARTY 3, then upon demand by YOUR COMPANY NAME, PARTY 3 agrees to issue a single party check payable to YOUR COMPANY NAME for the amount shown upon the unpaid invoice (s) relating to the goods/materials furnished to and used by  PARTY 2 under purchase order #: __________________________   dated: __________________.
Notwithstanding any additional contract terms that may now or hereafter exist between PARTY 2 and   PARTY 3, this agreement may not be altered or modified without the written consent of YOUR COMPANY NAME or its authorized representative.
This agreement will assist YOUR COMPANY NAME in fulfilling the requirements of PARTY 2 under its contract with   PARTY 3 and is for the mutual protection of each party. In no way should it be interpreted as casting doubt on the ability, integrity or credit worthiness of any interested party. Duly authorized signors should promptly execute this Agreement in the spaces provided below and upon completion, return this original Joint Check Agreement to YOUR COMPANY NAME. An acknowledgment will be mailed to you.

Your Company Name Party 2 Name            Party 3 Name           
By By By
Title Title Title

At-a-Glance: Joint Check Agreement Content Breakdown

  • The name and address of each party associated with the agreement
  • The name/address of the project to which the materials/labor are being supplied
  • The date the parties entered into the agreement
  • The credit terms
  • The steps to be taken, in the event the agreement is not upheld
  • Signatures of all parties involved

Although joint check agreements are an excellent tool for mitigating risk, there are potential pitfalls. Before entering into Joint Check Agreement, or any contractual agreement, it is always best to have legal counsel review the document & its terms.

No Preliminary Notice? No Mechanic’s Lien for You

No Preliminary Notice? No Mechanic’s Lien for You

About 40 states require a preliminary notice be served upon the owner of the property on which the contractor, subcontractor, or materialman is either performing work or furnishing materials.

Each state sets its own requirements for the preliminary or prelien notice, and state statutes are commonly highly specific as to the language required within the notice, the type of service allowed, and the timing provision of the notice.

A failure to provide the requisite prelien notice in a state where it is required can invalidate your mechanic’s lien.

Should Failure to Serve a Notice Invalidate a Mechanic’s Lien?

In a case arising out of the Court of Appeals in Minnesota, the court addressed the issue of whether a failure to serve a prelien notice on the property owner should invalidate a lien where the contractor claimed to be unaware of the true identity of the owner.

In the case of J. Roux Design & Associates, Inc. v. Backes, et al., Dennis Backes sold a property in Minnetonka, Minnesota to Superior Value Homes pursuant to an unrecorded deed, whereby Superior was to design and construct a residence on the property.  Superior entered into an oral agreement with Vogue Design & Realty, Inc. to design and construct the home.

The companies agreed Vogue would hire the subcontractors and Superior would pay them. Vogue contracted with Roux Design to do construction work on the home, and Roux used subcontractors and materialmen to complete the work.

A payment dispute arose between Roux and Vogue, and Roux filed a mechanic’s lien for approximately $26,000. Roux did not serve any prelien notices before filing the lien, nor did it serve the lien statement upon Superior at all. It served the lien statement only upon Backes and Vogue.

Superior sold the property shortly after the payment dispute between Roux Design and Vogue to Ulf and Anneli Henricksson.

Roux Design commenced lien foreclosure proceedings against all three defendants, Backes, Vogue, and the Henrickssons. The Henrickssons filed a third party complaint against Superior for indemnification, making Superior a party to the suit.

The defendants moved for summary judgment, claiming Roux’s lien must be discharged because it failed to file a prelien notice and failed to properly serve the lien statements. The district court granted the motion, finding Roux’s failure to serve the prelien notice on the owner of the property rendered the lien invalid.

“It held that a lack of knowledge as to the existence of an owner does not excuse the contractor from the prelien notice requirement”

Roux Appealed

On appeal, Roux asserted its lien should be found valid because at the time of contracting with Vogue it did not know Superior had an ownership interest in the property.  It contracted merely with Vogue and Vogue held itself out to be the owner.

The court, however, found this argument unpersuasive.  It held that a lack of knowledge as to the existence of an owner does not excuse the contractor from the prelien notice requirement. Roux had a duty to determine the identity of all owners and serve the requisite notice.

Further, Roux was paid by checks bearing Superior’s name. Therefore, a simple inquiry could have lead Roux to the knowledge of Superior’s ownership interests.

Roux’s ability to foreclose on its mechanic’s lien was invalidated due to its oversight concerning prelien notice.

Always review statute and serve the appropriate notice upon the appropriate parties via appropriate service.

What is a Bond Claim?

A Contractor Supplied a Payment Bond & You Haven’t Been Paid, What’s Next?

You supplied materials to the project, served a preliminary notice as required by statute, have not been paid. Now what?

It’s time to make a claim against the bond. But, what is a bond claim? Whose bond are you going to claim against? Can you only claim against a bond if it is a public project?  These are all great questions!

Before we explore and explain a bond claim, we need to define what a bond is and who the parties within the bond are.

What is a Surety Bond?

The Surety Information Office (SIO) defines a surety bond as “…a written agreement where one party, the surety, obligates itself to a second party, the obligee, to answer for the default of a third party, the principal…”

“Contract Surety Bonds provide financial security and construction assurance on building and construction projects by assuring the project owner (obligee) that the contractor (principal) is qualified to perform the work and will pay certain subcontractors, laborers and material suppliers”

A payment bond is a surety bond that is issued as assurance of payment to certain parties should the principal of the bond breach their construction contract.  If a subcontractor, supplier or materialman is unpaid for services, they may secure their receivables by serving a claim against the payment bond.

Here is an example of a federal payment bond:

Don’t get confused: a payment bond and a performance bond are two different bonds, though they are often issued together. The payment bond protects you when the contractor fails to pay; the performance bond protects the obligee when the principal fails to perform.

Bond Claims, Explained

A Bond Claim is a written notice informing the prime contractor and/or surety that the claimant (e.g. subcontractor, supplier or materialman) looks to them for payment.  Based on state statute, typically the bond claim must be served upon the general contractor and the surety, however, it is recommended to serve a copy of the bond claim on all parties involved. The more people that know you have not been paid, the more pressure these people will put on the appropriate party to encourage payment.

Frequently, a bond claim notice must be served within 90 days from last furnishing materials or services (e.g. Arizona). However, some state statutes, such as in Colorado, refer the claimant to the terms of the payment bond. (i.e. “Serve the bond claim notice in accordance with the terms and conditions of the payment bond.”)

Are All Contractors Required to Obtain a Bond?

The short answer is “No.”

Each state has its own statute requiring payment bonds on public projects and the Miller Act applies to payment bonds required on federal construction projects. Some statutes may require the general contractor obtain a payment bond on every construction project, and other statutes may only require a payment bond when the total value of the construction project exceeds a certain threshold.

True or False?  Bond claim remedies are only available on public or federal projects.

False! Payment bonds may be required or obtained for any project type. In fact, there are several states that have separate statute specific to bond claims on private projects:  Arizona, Arkansas, California, Florida, Georgia, Kansas, Louisiana, Mississippi, Nebraska, South Carolina, Texas, Utah & Wisconsin.

While a payment bond might not be required by statute on a private project, statute may apply as to the steps required to protect your rights under the private payment bond.  Further, it is possible that a subcontractor may be required, by the owner or the general contractor, to obtain a payment bond on a project!

Best Practice Tips

  • If a there is a payment bond on the project, attempt to obtain a copy of the bond at the time of contract.
  • Confirm the surety is on the Department of the Treasury’s Listing of Approved Sureties.
  • Review the payment bond to ensure you are covered as a potential claimant.
  • Serve applicable preliminary notices in accordance with statute.
  • If you remain unpaid, serve a copy of the bond claim upon all parties.
  • Keep all project documentation in a central location (e.g. invoices, delivery tickets, statement of account etc.)