3-in-3 on Lien Waivers

Today’s 3-in-3 Topic is on Lien Waivers

3-in-3 is a 3 question, 3 minute interview with an NCS colleague.

Today’s 3-in-3 features Notice & Lien Specialist, Amy Hunger.

While on a project you might be asked to supply a lien waiver. Often, an owner relies on that waiver before paying a general contractor to make sure that the subcontractors and material suppliers are being paid.

Waivers today are more formal and more complex and it’s very important to know exactly what you’re signing before you sign it.  Which leads us to our first question.

What should I be looking for when I’m being asked to sign a waiver?

Amy:  You always want to know what type of waiver you’re signing and whether it’s a partial or final waiver.  If it’s a partial waiver, confirm that the dollar amount is correct.  If the waiver includes the paid through date, be sure the dollar amount stated is right for that time period.

If it’s a final waiver, confirm that the pay amount stated is for all open invoices for that project.

You should also check the waiver to see if it is conditioned upon receipt and clearance of the payment made. The preferred waiver is a conditional waiver because if payment is not received or does not clear, the waiver will not be enforceable.

On the other hand, an unconditional waiver does not require receipt or clearance of the payment.  When an unconditional waiver is signed, your rights may be waived regardless of whether you received payment or whether payment clears the bank.

We’ve had quite a few projects where customers did not realize they were waiving their rights even if the check bounced.

Not every waiver contains the same type of wording so how do I know if it’s okay to sign it?

Amy:  When signing waivers, you must be very careful.  You want to read the entire waiver including the fine print.

If you’re unsure of what you’re signing, a legal opinion may be warranted to ensure that you’re not relinquishing your rights.

What is the difference between a lien waiver and a release of lien?

Amy:  That’s a very good question. Many use these terms interchangeably, but typically a waiver acknowledges payment, where a release of lien releases a previously recorded document.

A release will usually have specific wording listing the date the original document was recorded and the book and page number of where it was recorded.

A waiver is never a substitute for a release. If you had previously filed a lien, when you receive payment you need to release that lien and not just provide a lien waiver.

3-in-3 Takeaway

Carefully review every lien waiver before signing. Ensure the waiver follows statute and be cautious when signing unconditional lien waivers.

Did You Know? NCS clients have free 24/7 access to statutorily written lien waivers; you can generate, print and track lien waivers for every project!

Most Recent Resources

Blog

Will Safe Harbor Ever Exist for Florida UCC Filings? Zero Tolerance

Safe Harbor couldn't save this UCC. Florida's 'zero tolerance' policy means you must strictly comply with Article 9-503(a). Learn more here!
Read More
white paper
White Paper

NCS Credit Lien Index 2022 Q3

The Lien Index increased 4 points in Q3 2022, an 11% climb over Q2 2022. As expected, Q3 mechanic's lien activity rose 11% over Q2, and activity remained lower than Q1, which peaked at 43. We anticipate the Index will increase 2%-5% in Q4. Download the full report for details.

Read More
live webinars
Live Webinar

The Basics of the UCC Process

Worried about customers filing bankruptcy? Concerned about extending credit to marginal accounts? UCC filings secure collateral in agreement with your customer’s promise to pay.
Read More