A Material Supplier Wins in Recent Nevada Decision
It’s a win for the material supplier! A recent Nevada court decision invalidated an unconditional lien waiver when the subcontractor’s check to the material supplier failed to clear, leaving the material supplier unpaid.
The Case
Cashman Equip. Co. furnished specially fabricated materials to the Las Vegas City Hall project, and signed an unconditional waiver in exchange for payment from two higher tiered contractors, Mojave Electric and Cam.
Mojave Electric paid Cam and then Cam was to pay Cashman. Unfortunately, the first check Cashman received from Cam didn’t clear because Cam placed a stop payment on the check. The second check Cashman received from Cam didn’t clear due to insufficient funds.
Cashman did what was necessary to recover its money by filing a mechanic’s lien and then suit in the amount of $755,893.89. The trial court did award Cashman some funds (just under $300k based on an “equitable analysis”) but decided Cashman’s lien was unenforceable because of the executed unconditional lien waiver.
It Went to Appeal
Cashman was vindicated when the appeals court reversed the trial court’s decision, because it deemed the enforcement of an unconditional waiver, in this case, would violate Nevada’s public policy. Here’s what the judge had to say:
“The purpose of the mechanic’s lien statutes is to ensure payment to those who supply materials and labor on a project… Enforcing the unconditional waiver here would violate Nevada’s public policy, just like the pay-if-paid provision in the contract at issue in Lehrer violated public policy. And the very clear language of NRS 108.2457(5)(e) dictates that the waiver is void and unenforceable because Cashman never received payment. Here, Cashman’s agent testified at trial that he executed the lien release believing, despite the waiver language contained in the release, Nevada law would protect Cashman if Cam’s check did not clear the bank. The parties do not dispute that Cam’s check to Cashman did not clear the bank. Therefore, the waiver is void. Just as we refused to enforce the pay-if-paid provision in Lehrer, we likewise refuse to enforce Cashman’s release.”
Above, I mentioned Cashman had received some funds. This case also addressed “equitable fault” which authors Tracy DiFillippo and Kevin Stolworthy recapped in Nevada Supreme Court Ruling Means Additional Liability for Owners, Contractors and Subcontractors.
“The Court also rejected the application of the equitable fault analysis to reduce a mechanic’s lien. The trial court had initially found that Mojave and Cashman were innocent victims but found Mojave 33 percent responsible and Cashman 67 percent responsible for Cam’s actions. Based on the percentages, the trial court reduced the mechanic’s lien. On appeal, the Nevada Supreme Court concluded that equitable fault analysis was inappropriate to reduce the amount due under the mechanic’s lien.”
Be Careful!
Lien waivers can be precarious. We’ve discussed unconditional and conditional lien waivers before, and of course would always recommend parties sign conditional waivers as opposed to unconditional.