Lien is Late, Excessive, & Inaccurate, But It’s Not Frivolous

This Washington Lien Was Late, Excessive, and Inaccurate. But It Wasn’t Frivolous.

Late, excessive, inaccurate, but not frivolous: sounds like a terrible report card. You know the story, right? It’s about a mechanic’s lien filed in Washington which was initially invalidated and then reinstated by the Court of Appeals. How does a late, excessive, inaccurate lien get reinstated? Well, it’s a story worth sharing! (Spoiler: because it’s not a frivolous lien!)

Project-Condo-Dry-Out

Ongoing roof construction and an untimely rainstorm created quite a mess for more than a dozen condominium units. The property management company, MacPherson’s Property Management (MPM), hired Style Corporation dba Servpro (Servpro) for clean up and restoration work.

Servpro brought in its drying equipment & the equipment remained in the impacted condominium units for approximately two months. When the condominium association failed to pay Servpro for its services, Servpro filed a single lien for $183,945.09.

Servpro filed a single lien – not a lien on the individual impacted units. Within the lien, Servpro identified the debtor as the condo association, but the lien “applied to the 20 specific units and a common storage area where Servpro provided services.” Servpro also listed the 20 condo unit owners within the lien but did not indicate or allocate specific costs to each unit – the lien was a lump sum.

“Frivolous and Clearly Excessive”

It was the line held by PMP when it sought the release of Servpro’s lien: the lien is “frivolous and clearly excessive.” The court agreed and released the lien. But what kind of story would this be if it ended there? Servpro appealed the decision.

Court of Appeals on Frivolity

Per the Court of Appeals opinion:

“A lien is frivolous if ‘improperly filed beyond legitimate dispute’ and ‘so devoid of merit that it has no possibility of succeeding.’ Even if a lien is invalid, it may not be frivolous.”

A representative from MPM provided four reasons it believed Servpro’s lien was frivolous: 1) the representative from MPM did not authorize Servpro for ongoing work 2) Servpro’s lien was filed late 3) the agreement between MPM and Servpro did not dictate a contract amount as required by statute, and 4) Servpro’s lien was factually inaccurate.

Court of Appeals shot down MPM’s four reasons

The Oxford Comma Means Frivolous is Separate from Clearly Excessive

I must say, I did not see the Oxford comma making its way into a mechanic’s lien dispute. And yet, here we are! Washington’s mechanic’s lien statue, according to the Court of Appeals, clearly treats frivolous and clearly excessive separately under RCW 60.04.081(4).

The clear distinction lies in the comma between “cause” and “or” – actually, it’s the combination of the “,” followed by “or.”

Not to be outdone by the Oxford comma, the Court of Appeals also defined “clearly excessive” based on the dictionary definitions, because statute does not offer a definition.

Because Servpro did not break down the total claim amount by the number of units and filed its lien as though it were against one property vs. varying units, it appeared (for this case) a lien for $18k+ was filed against one unit, which makes Servpro’s lien clearly excessive.

The Court of Appeals concluded

The trial court erred by determining that Servpro’s lien was frivolous and releasing it. Although Servpro’s lien may ultimately be invalid and unenforceable, the narrow hearing authorized by RCW 60.04.081 does not allow for release of a lien based on invalidity alone.  Accordingly, we reverse the trial court’s ruling releasing the lien.

The court correctly concluded that Servpro’s lien was clearly excessive, but the court made no findings of fact about the amount by which the lien was excessive.”

What Could Servpro Have Done to Avoid this Mess?

Here are the actions Servpro could have taken to alleviate some of the issues:

  • Execute a Contract. While statute provides for an interpretation of a contact amount if it isn’t included in a contract, it may have alleviated some confusion if even an estimate was included.
  • Get the facts. Condominiums and mechanic’s liens can be a major pain. Title work can be cumbersome and expensive, but it provides critical information. If Servpro had correctly identified the property/units and allocated costs to each unit, it may have escaped the “clearly excessive” issue.
  • File a lien on time! In Washington, the mechanic’s lien should be filed within 90 days from last furnishing.

This case is on its way back to the trial court where it will likely be invalidated because of timeliness and an excessive claim, but at least we now know it wasn’t a frivolous lien.

Most Recent Resources

Blog

No Lien Rights for Rental Equipment Companies in Pennsylvania

Review this recent Pennsylvania legal decision and how UCC filings are poised to be the payment leverage rental equipment companies need.
Read More
white paper
White Paper

Healthcare Bankruptcies: A Financial Risk to Suppliers

Learn how creditors providing everything from basic office supplies to extensive operating room equipment have an opportunity to file a UCC to recover funds and repossess equipment.

Read More
live webinars
Live Webinar

The Importance of Gathering Job Information

Do you realize the importance of obtaining job information as it relates to the protection of your lien and bond claim rights?
Read More