Waiving Bond Claim Rights Under The Miller Act

Are You Waiving Your Bond Claim Rights Under The Miller Act?

If you furnish to a federal construction project, and your contract includes a provision for claim resolution outside of the Miller Act, are you prohibited from pursing a claim under the Miller Act? Are you waiving your rights? Short answer: No. Unless

Miller Act Statute

The statute for federal projects is relatively straightforward and applies to all states; meaning unlike state statutes which vary, federal statute is the same across the board. U.S. Federal projects in foreign lands may also fall under the protection of the Miller Act.  Those furnishing to a federal project are not required to serve a preliminary notice, but a bond claim should be served with 90 days after the date of last furnishing, and suit should be commenced within one year after the date of last furnishing.

Typically, the general contractor is required to obtain a payment bond if the construction contract exceeds $100,000. And, would-be claimants can request a certified copy of the payment bond from the contracting agency.

3133. Rights of persons furnishing labor or material

(a) Right of Person Furnishing Labor or Material to Copy of Bond. – The department secretary or agency head of the contracting agency shall furnish a certified copy of a payment bond and the contract for which it was given to any person applying for a copy who submits an affidavit that the person has supplied labor or material for work described in the contract and payment for the work has not been made or that the person is being sued on the bond…

Waiving Rights in a Contract

If your contract calls for alternative dispute resolution or waives rights in lieu of action under the Miller Act, does this mean you have lost your rights under the Miller Act?

This is a hot topic in construction: waiving rights to mechanic’s liens and bond claims. Some statutes clearly define whether rights are waived or if the waiver of rights is enforceable, while others are clear as mud. Fortunately, for federal projects, it’s not overly complicated. Yes, rights can be waived; however, the waiver must be in writing and it can’t be executed until after the claimant has completed furnishing.

3133. Rights of persons furnishing labor or material

(c) Waiver of Right to Civil Action. – A waiver of the right to bring a civil action on a payment bond required under this subchapter is void unless the waiver is-

(1) in writing;

(2) signed by the person whose right is waived; and

(3) executed after the person whose right is waived has furnished labor or material for use in the performance of the contract.

Earlier I said that federal statute is the same in all states, and while this is true, the courts hearing federal cases may not make the same decisions. So, when I say “Yes, rights can be waived” I’m taking statute at its word – no gray area. But, as you know, in construction credit, there is a LOT of gray area.

Christopher M. Horton, associate with Smith Currie, recently wrote an article, Does the Miller Act Trump Subcontract Dispute Provisions? In his article, Horton discusses a few examples of different states and their stance on whether a contract can prevent someone from pursuing a Miller Act claim.

“…[C]ourts have considered whether subcontract provisions requiring exhaustion of dispute procedures prior to initiating a Miller Act suit conflicts with the waiver provisions of the Miller Act. Only a few federal courts have addressed this issue… (D.C., Maryland, Nebraska, New Jersey, Pennsylvania, Virginia), have found that such provisions are unenforceable and do not require dismissal or stay of a Miller Action lawsuit.

A minority of courts (Louisiana, California, and Hawaii) have upheld dispute exhaustion provisions and entered dismissals or stays of Miller Act. Contrary to the decisions referenced above, the courts rendering these decisions based their rulings upon the fact that the provisions at issue included express language that required a stay for Miller Act claims pending exhaustion of the dispute procedures…. The subcontractor’s Miller Act remedies remained intact pending exhaustion of the contractual dispute procedures.”

OK, so, perhaps my statement about federal statute being clear was a tiny bit inaccurate — turns out, it can get quite muddy. Though, it seems, at least based on Horton’s article, that courts may allow claimants to pursue a Miller Act claim even if alternative dispute options are identified in the contract.

Best advice? Before you sign the contract, carefully review it with legal counsel. Do not blindly sign a contract, assuming it will all pan out.

Most Recent Resources

Blog

No Lien Rights for Rental Equipment Companies in Pennsylvania

Review this recent Pennsylvania legal decision and how UCC filings are poised to be the payment leverage rental equipment companies need.
Read More
white paper
White Paper

Healthcare Bankruptcies: A Financial Risk to Suppliers

Learn how creditors providing everything from basic office supplies to extensive operating room equipment have an opportunity to file a UCC to recover funds and repossess equipment.

Read More
live webinars
Live Webinar

The Importance of Gathering Job Information

Do you realize the importance of obtaining job information as it relates to the protection of your lien and bond claim rights?
Read More